Equinor Files Plan to Electrify Troll West Field

Share:

Norway's Equinor, with partners Petoro, Shell, Total, and ConocoPhillips, has decided to electrify the Troll West field offshore Norway and has submitted the plan for development and operation to the Norwegian minister of petroleum and energy. 

The decision includes partial electrification of the Troll B platform and full electrification of Troll C in the North Sea. 

The subsea cable to the Troll B and C platforms will have a landfall at Kollsnes in Øygarden west of Bergen.  A high-voltage subsea cable will run from Kollsnes to Troll B, and one from Troll B to Troll C.

Troll West electrification includes full electrification of Troll C, and partial electrification of Troll B. This means that both platforms’ current power demand will be met from shore. In addition, the two gas export compressors on Troll C currently driven by gas turbines will be replaced by electric motors. The infrastructure at Kollsnes and cable out to the platform will be designed for a possible future full electrification also of Troll B.

The Troll A platform, which came on stream in 1996, was the first electrified installation on the NCS.

Capital expenditures for the Troll West electrification project total about NOK 7.9 billion (around $949 million). The project has been pledged a total of NOK 520 million (around 62,5 million) in financial support from the Norwegian NOx fund.

"This will cut CO2 emissions by almost half a million tonnes per year, i.e. the equivalent of more than three percent of total emissions from oil and gas production and one percent of total emissions in Norway. NOx emissions from the field will be reduced by some 1700 tons per year," Equinor said.



“Electrification is essential to successful reduction of the emissions from the [Norwegian Continental Shelf ], and we have ambitious plans for this. The partnership’s decision to electrify Troll B and Troll C will cut emissions substantially. The Troll area will deliver enormous volumes of low-emission energy for many decades, adding great value for the companies and for Norway,” said Kjetil Hove, Equinor’s executive vice president for Development & Production Norway.

"I am very pleased that we can realize Troll B and C electrification, a project that will help cut emissions on the NCS significantly. I am also pleased that we, in these challenging times, are able to sanction projects that help create great value for society and valuable activity for the suppliers. We expect that about 70 percent of the investments in this project will go to companies in Norway, said Arne Sigve Nylund, Equinor’s executive vice president for Technology, Projects & Drilling.

“The temporary changes to the petroleum tax regime adopted by Parliament as a result of Covid-19 have enabled us to implement several of the projects planned prior to the pandemic,” Nylund said.

Aker EPCI for Troll Topsides

Aker Solutions has been awarded an engineering, procurement, construction and installation (EPCI) contract for modifications enabling the Troll B and C topsides to receive power from shore.  Worth around NOK 2.9 billion the contract will generate about 1000 man-years of work for the supplier during the project period. Engineering will be performed from Aker Solution’s Bergen office, and construction will take place at the Stord yard. The supplier estimates that a total of 4000 people will be involved in the work, including sub-contractors.

Skanska has been awarded a contract for the construction of a new transformer substation, cable trenches and landfall at Kollsnes. The contract is worth around NOK 390 million. The work will be headed by Skanska’s construction division in Bergen. The project is estimated to generate around 100 man-years of work for Skanska and sub-suppliers during the project period.

NKT has been awarded a contract for the production and installation of a high-voltage subsea cable from Kollsnes to Troll B and from Troll B to Troll C. The contract is worth about NOK 1 billion. Cable production will take place at their factory in Karlskrona, Sweden, and they will use their vessel NKT Victoria for the cable laying work.

On March 26, 2021 the Ministry of Petroleum and Energy granted Equinor a concession to construct, own and operate the necessary electrical installations to supply the Troll B and Troll C platforms with power from shore. The power requirement for Troll B and C will be up to 116 MW.

According to the plan, Troll B will be partially electrified in the first quarter of 2024, and Troll C will be fully electrified by the second quarter of 2026.

No comments

More Popular Posts

About Crude Oil Brokers Ltd

Crude Oil Brokers Ltd is a dedicated global broker and facilitator of crude oil buying and selling. We work directly with crude oil buyers and crude oil sellers worldwide. We are a United Kingdom and Nigerian based firm, privately owned and devoted to the brokering of crude oil and other petroleum products buying and selling.

We have buyers and sellers of;

1. Nigerian Bonny Light Crude Oil, BLCO

2. D2 Diesel Fuel, JP54 Jet Fuel, Mazut etc.

3. Saudi Light Crude Oil, SLCO

4. Iraqi Light Crude Oil

If you are a buyer or seller of crude oil or other petroleum products or have mandate to buy or sell any of the above oil products, do contact us because we could be of help.

To contact Crude Oil Brokers, click here ». To learn more about Crude Oil Brokers Ltd, click here


Crude Oil Brokers